Florence Hummerston Reserve Enhancement Project 

Duration: May 2011 - August 2011 +12months Maintenance Period

Client: City of Perth

Details: Landscaping and Streetscaping of Florence Hummerston Reserve, including;

  • Installation of lighting and electrical works,

  • Civil works for landscaping preparation,

  • Protection of existing trees,

  • Installation of new reticulation systems,

  • reticulation bore and pump cabinet with rain bird controllers,

  • Placing of new plants and trees and associated ground works.

 

Major Projects

St Georges Terrace Streetscape Project

Duration: February - May 2010

Client: Broad Construction

Details: Supervision and completion of all street scape elements including;

  • installation of new trees and plants,

  • excavation for road pavement works,

  • supply and placement of new asphalt,

  • preparation and line markings,

  • granite kerbing, granite paving and

  • drainage works.

 

Mounts Bay Road Two Way Upgrade

Duration: August  - December 2014

Client: City of Perth

Details: The purpose of this project is to allow for two way traffic flows along Mounts Bay Road in order to give commuters alternative routes, making navigating the city easier and safer for pedestrians and cyclists. This project has included earthworks, preparation and laying of asphalt for a new cycle path, road widening, and drainage alteration/installation, removal of trees, removal and installation of kerbing

 

Town of Victoria Park
Memorial Wall Construction

Duration: November 2014 - April 2015

Client: Town of Victoria Park and RSL

Details: Construction of a new memorial wall to honor Australians who served in WW1, as well as brick paving, erection of flagpoles, installation of new lighting,

 